CHINA: MTR Corp signed an agreement in principle on January 16 with the Hangzhou Municipal Government and Hangzhou Metro Group for the financing, construction and operation of Line 1 of the metro under a PPP model.
The agreement allows MTR to enter into further discussion with the city government over the detail of the concession, which includes rights to operate Phase 1 of the line for 25 years.
The 22bn yuan project is to be divided into two parts, A and B, covering approximately 63% and 37% of the work respectively. Part A covers civil works, and will be undertaken by Hangzhou Metro Group. Preparatory works began in March 2007. Part B largely covers the supply of electrical and mechanical equipment and the operational element, to be undertaken by the Co-operative Joint Venture of Hangzhou Metro Group and MTR Corp, which has a 49% stake.
One of eight planned routes, Line 1 will be 48 km long, of which 41 km will be underground. Running north-south and serving 30 stations, it will link Hangzhou to the satellite cities of Xiasha, Linping and Jiangnan. It is scheduled to open in 2012.
Register here to receive the free Railway Gazette Weekly e-newsletter and keep up to date with the latest industry news.
Translate this page in your language: