Work on a single route from Saint Roch by the old city to Saint Chamand in the southeast (Line T1: 5·2 km, 10 stops) began in October 2016; test running started in May 2019 and the line opened on October 19, 2019. Work was led by NGE Group subsidiary TSO, the consortium includes Alstom, Guintoli, EHTP and Agilis.

A second route is planned, with construction to start in 2021 for opening in 2023. Line T2 would run from Piot east to Saint-Lazare- Université Arendt (3·2 km, 7 stops); Alstom would supply four more LRVs.